Close

1. Identity statement
Reference TypeJournal Article
Siteplutao.sid.inpe.br
Holder Codeisadg {BR SPINPE} ibi 8JMKD3MGPCW/3DT298S
Identifier8JMKD3MGP3W/3TEPQ6H
Repositorysid.inpe.br/plutao/2019/06.10.16.46
Last Update2019:06.13.13.28.49 (UTC) lattes
Metadata Repositorysid.inpe.br/plutao/2019/06.10.16.46.23
Metadata Last Update2021:07.15.05.09.30 (UTC) administrator
DOI10.5028/jatm.v11.1031
ISSN1984-9648
Labellattes: 1304704585952173 2 SantosFerr:2019:ApCOII
Citation KeySantosFerr:2019:ApCOII
TitleApplying COCOMO II for a DO-178C safety-critical software effort estimation
Year2019
Access Date2024, May 18
Type of Workjournal article
Secondary TypePRE PN
Number of Files1
Size1123 KiB
2. Context
Author1 Santos, Lucas Pereira
2 Ferreira, Maurício Gonçalves Vieira
Resume Identifier1
2 8JMKD3MGP5W/3C9JHT8
Group1 DIDSE-CGETE-INPE-MCTIC-GOV-BR
2 COCRC-COCRC-INPE-MCTIC-GOV-BR
Affiliation1 Instituto Nacional de Pesquisas Espaciais (INPE)
2 Instituto Nacional de Pesquisas Espaciais (INPE)
Author e-Mail Address1 lucas.pds@gmail.com
2 mauricio.ferreira@inpe.br
JournalJournal of Aerospace Technology and Management
Volume11
Numbere1819
History (UTC)2019-06-10 16:46:23 :: lattes -> administrator ::
2019-06-10 17:22:47 :: administrator -> lattes :: 2019
2019-06-13 13:28:51 :: lattes -> administrator :: 2019
2021-07-15 05:09:30 :: administrator -> simone :: 2019
3. Content and structure
Is the master or a copy?is the master
Content Stagecompleted
Transferable1
Content TypeExternal Contribution
Version Typepublisher
KeywordsSoftware development
Software engineering
Project management
Engineering management
Cost estimates
AbstractThis paper provides a real example of applying COCOMO II as an estimation technique for the required software development effort in a safety-critical software application project following the DO-178C processes. The main goal and contribution of the case study is to support the research on software effort estimation and to provide software practitioners with useful data based on a real project. We applied the method as it is, by correlating the effort multiplier factors with the complexity and objectives introduced by the DO-178C level A application, resulting in an estimated effort. The rationales for each scale factor and effort multiplier selection were also described in detail. By comparing the estimated values with the actual required data, we found a magnitude of relative error (MRE) of 40% and provided alternatives for future work in order to increase the effort estimation accuracy in safety-critical software projects.
AreaETES
Arrangement 1urlib.net > BDMCI > Fonds > Produção anterior à 2021 > COCRC > Applying COCOMO II...
Arrangement 2urlib.net > BDMCI > Fonds > Produção anterior à 2021 > DIDSE > Applying COCOMO II...
doc Directory Contentaccess
source Directory Contentthere are no files
agreement Directory Contentthere are no files
4. Conditions of access and use
data URLhttp://urlib.net/ibi/8JMKD3MGP3W/3TEPQ6H
zipped data URLhttp://urlib.net/zip/8JMKD3MGP3W/3TEPQ6H
Languageen
Target File2175-9146-jatm-11-e1819.pdf
User Grouplattes
Reader Groupadministrator
lattes
Visibilityshown
Archiving Policyallowpublisher allowfinaldraft
Update Permissionnot transferred
5. Allied materials
Next Higher Units8JMKD3MGPCW/3F3PAJE
8JMKD3MGPCW/446AUSL
Citing Item Listsid.inpe.br/mtc-m21/2012/07.13.14.56.30 2
sid.inpe.br/bibdigital/2013/10.19.00.29 2
sid.inpe.br/bibdigital/2021/02.11.20.54 2
DisseminationWEBSCI; PORTALCAPES; COMPENDEX; SCOPUS.
Host Collectiondpi.inpe.br/plutao@80/2008/08.19.15.01
6. Notes
Empty Fieldsalternatejournal archivist callnumber copyholder copyright creatorhistory descriptionlevel e-mailaddress format isbn lineage mark mirrorrepository month nextedition notes orcid pages parameterlist parentrepositories previousedition previouslowerunit progress project readpermission rightsholder schedulinginformation secondarydate secondarykey secondarymark session shorttitle sponsor subject tertiarymark tertiarytype url
7. Description control
e-Mail (login)simone
update 


Close